Case Study

Synchronous Motors for Compressor Drives

Powering the world’s second largest sub-sea pipeline delivering over 20% of UK gas



Over 15 years of
reliable, efficient,
zero emission
performance, in an
industry-changing
application.

Profile

Ormen Lange, which translated means “Long Snake”, is located 120km off the northwest coast of Norway at a water depth of 800 – 1100 metres.

It is Norway’s second largest gas field with estimated gas reserves of 395 billion cubic meters, and an annual production of 20 billion cubic metres. Gas production from the Ormen Lange Field on the Norwegian continental shelf started on 13th September 2007.

Powering the world’s second-longest sub-sea gas pipeline

At the heart of this historic project, to deliver gas via the 1200km “Langeled” sub sea gas pipeline, the second longest in the world, from Nyhamna in Norway to Easington on the UK east coast, are four 48MW export gas compressors driven by BRUSH MAX 2-pole synchronous motors.

Operating at speeds between 2,520 rpm and 3,780 rpm, these closed circuit air to water (CACW) cooled MAX motors are a derivative of the very successful BRUSH DAX range of turbogenerators.

The motors are configured for variable speed operation powered by a load commutated inverter (LCI).

“The units are working to plan with no issues, a real credit to BRUSH engineering and build”

Project Manager, Ormen Lange

As part of the customer’s rigorous testing programme for these machines, certified for hazardous area operation, the motors were required to perform a 48MW full load, full speed, back to back test with the project drive equipment. In addition, a variable speed, full load string test was carried out with the contract compressor equipment.

The project, seen as one of the industry’s most successful development programmes, delivered on time and on budget. Today the facility is operated by Norske Shell and delivers over 20% of the UK’s gas.

Nyhamna Gas Plant

Resources

Related News

CASE STUDY

BRUSH Generators at Extreme Altitudes

BRUSH was asked to provide generators for a location in Chile specially adapted for the high altitude in the Atacama Desert



BRUSH generators provide assured power and are essential where reliability is paramount.

Profile

Geothermal power production is a form of renewable energy generation that harnesses thermal energy from underground sources.

Boreholes are drilled into the geothermal source and water is injected at pressure to be heated. The water returns in the form of steam, which is used to drive geothermal steam turbines. The driver in turn, rotates a generator which produces electrical power.

The thermal energy must be of a certain temperature to be suitable for power generation, and the location of the energy sources meeting this requirement are often in environmentally challenging locations.

The Challenge

BRUSH was asked to provide generators for a location in Chile specially adapted for extreme conditions. The location of the site was at high altitude in the Atacama Desert at 4,500m. At these altitudes the air is much thinner and had high levels of hydrogen sulphide (H2S) and sulphur dioxide (SO2) gases. We called on our long experience in designing engineered solutions for generator applications to meet this challenge.

The Solution

Ensuring the equipment used to produce the power could endure harsh elements was imperative, so we supplied two specially modified, 27.6MW, four-pole, 1,500r/min generators with a rated voltage of 9,500V and a power output of 32.5MVA. Each of the dual-shaft generators were powered by two 15MW turbines and designed to withstand the challenges presented by extracting geothermal energy in 4,500m conditions.

At high altitudes the air is much thinner which can increase the potential for damaging partial discharge activity in the stator winding.

Our design team developed a solution that de-rated the generation voltage to reduce the risk of stator damage, while maintaining the specified power output. This means that the generators will be kept online by optimising the stress on the electrical insulation system

We evaluated solutions for generator cooling due to the thinner air, this was complicated by both the ambient temperatures at extremes lows of -31°C, and the presence of toxic H2S and SO2 gases.

To counter these threats, we designed a pressurisation system that provided clean air to the inner part of the generators and that featured a special filtration system to neutralise the H2S and SO2 gases. Specialized heating was installed to keep the generator warm during times when the system was idle.

This application location also presented human challenges. Service personnel could only be present at such extreme altitudes for short periods of time without suffering from altitude sickness. This meant installation, and later maintenance, had to be carefully planned and scheduled with the operator. Strict guidelines were put in place to ensure the safety and health of the team.

The Result

We completed the design and build within the agreed delivery lead time, and power output specification. In doing so, we contributed to the first power plant built at this altitude worldwide, increasing the number of locations that can be considered for geothermal energy production.

When you have a challenging power generation application contact BRUSH to discuss our solutions.

More Case Studies

PROJECT AWARD

BYE-Guangzhou Metro BT

Hawker Siddeley Switchgear (now BRUSH Switchgear) has, in partnership with BYE, been awarded the opportunity to supply a total of 443 NDC Circuit Breakers across lines 21, 14 and Knowledge City line

Profile

Guangzhou Metro is the metro system of the city of Guangzhou in Guangdong Province of China. It was the fourth metro system to be built in mainland China, after those of Beijing, Tianjin and Shanghai.

Having delivered 2.054 billion rides in 2013, Guangzhou Metro is the sixth busiest metro system in the world, after the metro systems of Tokyo, Seoul, Moscow, Beijing, and Shanghai and operates 164 stations.

The city, in the south of one of the world’s most populous countries, was initially planned to have a two-line metro system, which uses some of the latest light-rail technology, and was a model for a completely integrated project.

The number of lines was, however, increased later. The metro now operates eight lines, with an additional six lines underway.

The Challenge

Guangzhou Metro is now undergoing an expansion project increasing the metro by 16 lines with a length of 432.6km by 2025 in order to connect their rising areas. It is estimated that the total investment will reach 297.6 billion yuan.

Key Benefits

Quick turnaround
Solve site delivery restrictions
Express turnaround times

The Solution

Hawker Siddeley Switchgear (now BRUSH Switchgear) has, in partnership with BYE, been awarded the opportunity to supply a total of 443 NDC Circuit Breakers across lines 21, 14 and Knowledge City line. Totalling 166,526,302 yuan.

182 NDC Circuit Breakers will be supplied to Line 14 Phase 1. Line 14 runs from the North to the South of the city with 54.4km of track.

201 NDC Circuit Breakers will be supplied to Line 21. Line 21 is 61.5km which covers areas that are underground and through mountains. Finally 60 NDC Circuit Breakers will be supplied to the Knowledge City Line which is 21.9km.

The Result

An ongoing partnership for BYE’s future projects and a more secure metro line at the heart of China’s traction distribution system.

Providing Guangzhou Metro a safe, reliable, low maintenance solution.

Resources

More Case Studies

CASE STUDY

BRUSH Solves Urgent Customer Problem in Record Time

Exceptional service to restore DNO network resilience

Profile

A leading UK Distribution Network Operator (DNO) notified BRUSH that due to a failure on one of their distribution sites, an urgent requirement was the installation of their strategic spare 15/30MVA, 33/11KV Power transformer.

The Challenge

Brush visited the site on the next working day to assess the requirements and it was evident that the compact spare unit would require converting to separate coolers . The transformer had been held in storage at BRUSH (since 2013) as a strategic spare. The client notified BRUSH that the failed unit must be replaced and the new unit energised within four weeks to avoid any risk to their network. A further challenge for BRUSH was to overcome the width restrictions on route to the site within the already reduced timescales.

The Solution

The stored transformer was originally built as a compact unit, meaning all the ancillary details were tank mounted. The DNO specified a separate cooler bank assembly to match the failed unit, and the transformer required reconfiguring prior to any in-factory testing. The transformer was immediately removed from the BRUSH on site storage facility and taken into the factory for work to commence. The transformer was successfully converted from a compact design to a separate cooler bank.

Following the mechanical build of the transformer within the BRUSH factory, a second Factory Acceptance Test (FAT) was carried out to ensure the unit was functioning correctly prior to despatch to site. Additionally, the transformer was subject to full oil processing and a complete re-spray.

Key Benefits

Quick turnaround
Solve site delivery restrictions
Express turnaround times

“As you know we were all very impressed and appreciative of the sterling efforts from all your goodselves at BRUSH in helping us achieve a prompt and safe replacement of C1MT at Bradford on Avon back in September / October 2019”

Scottish & Southern Electricity Networks

Following a site visit, it was agreed between the client, BRUSH and the heavy haulage contractor that due to width restrictions on route to site the transformer would have to be transported at a maximum width of 2.75 metres, requiring the unit to be stripped to the minimum width. To achieve this, the HV, LV and neutral cable boxes, disconnecting chamber, tapchanger, auxiliary transformer and cooler control cubicle were removed.

The Result

BRUSH Transformers Service Team successfully delivered the Transformer to site ahead of schedule and worked for ten consecutive days to re-build the Transformer. The Mechanical installation included the previously removed HV, LV & Neutral cable boxes, Disconnecting chamber, Auxiliary Transformer, Tapchanger in addition to the full cooler bank assembly.

Other duties included all Wiring, Oil handling and Cold Commissioning. BRUSH also carried out a full ratio on the Tap changer due to disconnection for transport. Upon completion, the Transformer was handed over to the DNO a week ahead of schedule. The Transformer was successfully energised in October 2019 and BRUSH Transformers Service Team received high praise from the client for the handling of the project, resulting in another BRUSH Transformer becoming part of the network ahead of schedule.

More Case Studies

CASE STUDY

BRUSH Commissioned for Major 2-Pole Generator Update

As the world’s largest independent manufacturer of generators above 20MVA, we were proud to be commissioned by current operators of the power station to carry out a major overhaul of their BDAX 9-450PRH generator.

Profile

BRUSH And An Established UK Power Station Share A Long History.

We originally manufactured two GT units and one ST unit in the early 1990s. These generators are still in operation today as peaking units to support the UK grid.

As the world’s largest independent manufacturer of generators above 20MVA, we were proud to be commissioned by current operators of the power station to carry out a major overhaul of their BDAX 9-450PRH generator.

Given our proven track record and unrivalled experience in the production and servicing of 2-pole generators – that perform such a vital function in power stations around the world by converting the mechanical energy created by the turbine into electricity – we were the obvious choice.

The Solution

The scale and scope of the project was huge, but we have the capacity and expertise to meet even the most challenging of deadlines.

Our service engineers began by dismantling the generator on site before removing the rotor and taking it back to our factory. The endcaps were removed and after a thorough inspection and clean, the rotor was carefully reassembled before being balanced in our specialist overspeed pit facility.

Key Benefits

Quick turnaround
Solve site delivery restrictions
Express turnaround times

Meanwhile, our team inspected and cleaned the generator’s stator before putting it through a series of rigorous tests.

Once all of this was complete, we returned the rotor to site, where we reassembled and commissioned the generator before handing it back to the owner.

The Result

In a world where time is money, we completed the whole project in just 10 weeks, thanks to the efficiency of our service and the expertise and dedication of our team.

Successfully back up and running, the generator now helps provide power to approximately 500,000 homes, thanks in no small part to BRUSH.

CASE STUDY

BRUSH Conducts Mid-Journey Generator Repairs for Major Cruise Ship

While passengers are enjoying a trip of a lifetime, a staggering array of complex and powerful machinery is working below deck on cruise ships.



BRUSH generators provide assured power and are essential where reliability is paramount.

Profile

While passengers are enjoying a trip of a lifetime, a staggering array of complex and powerful machinery is working below deck on cruise ships. While the ship’s engineers are well-trained to solve most issues with ease and ensure easy travel from port to port, sometimes equipment urgently requires expert attention. In this case, the vessel contacted BRUSH experts who are available to provide technical support 24/7.

The Background

One of our customers, an operator of a world-renowned cruise line, noted that there were increasingly high temperature readings on a critical bearing, they quickly contacted us through our Service 24™ program.

The Solution

Our customer carried out basic testing and deduced that the bearing likely needed to be replaced. Fortunately, they had stocked critical spares including a spare bearing on-board, but they had not stocked the essential bearing accessories such as jacking oil pipes and non-return valves.

Key Benefits

Quick turnaround
Solve site delivery restrictions
Express turnaround times

As time was of the essence, we quickly organized a plan to deliver the necessary parts to the vessel. The parts were gathered, and since the hoses were on the critical path, to keep the turnaround time a fast as possible, we had them manufactured at extremely short notice. These parts covered both the gas turbine driven generators on the vessel.


One of our engineers was able to travel to the ship within a few days with the spare parts, providing an extremely fast plant-to-craft delivery.

The Result

On inspection, the bearing was found to be worn from adverse operating conditions, after being in service without issue for 15 years. While aboard, our engineer was able to identify several other minor issues and advised the customer on the best course of action to get the problems fixed.

BRUSH generators provide assured power and are essential where reliability is paramount. The job was completed successfully, and our engineer returned home leaving a satisfied customer to set sail.